Tech Tool Blog -- Project Management
Dear Mr. Peterson,
I was contacted by the famous scooter company , ARC, to help them construct a Gnatt Chart to assist in the development of their new RED STREAK Scooter. They commissioned me to test out the free online software known as TeamGnatt for the construction of the Gantt Chart. It's usability is okay, but appears to only give the bare bones options for the free users. This means that some of the key features are not given to the free user, and the software is not nearly as efficient as it could be. Another draw back of the software is the lack to automatically account for federal holidays, or even preset holidays. It seems like such an easy feature to implement, yet it could be behind the pay wall. I would say the program would take an average person with an average technical know how about 4 hours of proper training before they feel comfortable with the software.
As for ARC's Gantt Chart here it is:
I was contacted by the famous scooter company , ARC, to help them construct a Gnatt Chart to assist in the development of their new RED STREAK Scooter. They commissioned me to test out the free online software known as TeamGnatt for the construction of the Gantt Chart. It's usability is okay, but appears to only give the bare bones options for the free users. This means that some of the key features are not given to the free user, and the software is not nearly as efficient as it could be. Another draw back of the software is the lack to automatically account for federal holidays, or even preset holidays. It seems like such an easy feature to implement, yet it could be behind the pay wall. I would say the program would take an average person with an average technical know how about 4 hours of proper training before they feel comfortable with the software.
As for ARC's Gantt Chart here it is:
Here are the questions ARC wanted me to answer.
1.
When is the project estimated to be completed? How long
will the project take?
The project will be done by January 22nd
2018 and the project will take a year and 22 days to complete
2.
What is the critical path for the project?
The Critical path follows the gantt chart exactly
up until the 2 way split. It then follows Final Design Selection. The next break is at the 3 way split. The critical path then follows the creation of the
Detailed product design , then back to how the normal gantt chart presents
itself.
3.
Which activity has the greatest amount of slack?
The Activity with the greatest
amount of slack is the creation of the detailed marketing plan.